Guide

ODC transport in India: a planning guide

In India, a load is over-dimensional (ODC) or over-weight (OWC) when it cannot be carried within the vehicle size limits of rule 93 of the Central Motor Vehicles Rules, 1989, or the axle-weight limits notified by the Ministry of Road Transport and Highways (MoRTH). On National Highways, a single indivisible load on modular hydraulic trailers moves under an online MoRTH permission.

This guide sets out the limits, permits, documents, route and bridge checks, escorts and timelines as of October 2026, with the official sources listed at the end.

When is cargo over-dimensional?

Rule 93 of the Central Motor Vehicles Rules, 1989 sets the maximum width, length and height of each vehicle category. Cargo that would take a vehicle past these limits is over-dimensional cargo (ODC).

For an indivisible load, rule 93 allows two relaxations. The load may project 200 mm beyond each side of a vehicle 2.6 m wide, with the projecting part painted or taped in yellow and black reflective marking and a red lamp at the rear and a white lamp at the front of each extreme end. The vehicle may also be up to 4.75 m high.

Rule 93 defines an indivisible load as cargo that cannot be divided without extreme effort, expense or risk of damage, and cannot be carried without exceeding the permissible mass or dimensions of the vehicle and roads.

Rigid goods vehicle (N2, N3)
2.6 m wide, 12 m long, 4.0 m high (some body types differ)
Semi-trailer with tractor, truck-trailer
2.6 m wide, 18.75 m long, 4.0 m high (some body types and loads differ)
Goods vehicle carrying an indivisible load
Up to 4.75 m high; 200 mm projection each side on a 2.6 m wide vehicle
Modular hydraulic trailer, one module of up to 8 axle rows
3.0 m wide, 19 m long, 4.75 m high
Modular hydraulic trailer with puller tractor
3.0 m wide, 29 m long, 4.75 m high
Puller tractor with three or more axles
2.6 m wide, 10 m long, 4.2 m high
Mechanical trailer of exceptional length, with puller
3.0 m wide, 29 m long, 4.0 m high; trailers up to 18.75 m may extend to 50 m for the length of an indivisible load

Axle-load and weight limits

MoRTH notification S.O. 3467(E) of 16 July 2018, as amended by S.O. 3881(E) of 6 August 2018, sets the maximum safe weight for each axle type under section 58 of the Motor Vehicles Act, 1988, and caps gross vehicle weight. Cargo that would take a vehicle past these weights is over-weight cargo (OWC).

On single axles with four tyres, and on tandem axles and tri-axles of rigid vehicles and trailers, pneumatic suspension allows 1 tonne more per axle. Modular hydraulic trailers may carry indivisible goods of any weight, subject to the regulatory approvals required. S.O. 3467(E) limits each axle row of a modular hydraulic trailer to 18 tonnes, and MoRTH’s National Highway permissions apply the same limit.

Single axle, four tyres
11.5 t
Tandem axle, rigid vehicle or trailer
21 t
Tri-axle, rigid vehicle or trailer
27 t
Tandem axle, puller tractor for hydraulic or pneumatic trailers
28.5 t
Axle row of a modular hydraulic trailer (two axles, four tyres each)
18 t (9 t per axle)
Gross vehicle weight, rigid vehicle
49 t maximum
Gross vehicle weight, semi-articulated or truck-trailer
55 t maximum (modular hydraulic trailers excepted)

Who issues ODC permits

On National Highways, MoRTH grants online permission for a single indivisible ODC/OWC consignment on modular hydraulic trailers, types HT-1 to HT-13, through its ODC/OWC portal at morth-owc.nic.in. Regional officers of MoRTH, the National Highways Authority of India (NHAI) and the National Highways and Infrastructure Development Corporation (NHIDCL) review the bridges on the route.

Roads that are not National Highways need permission from the authorities with jurisdiction over them. MoRTH’s 2018 advisory on axle weights says modular hydraulic trailers carrying single indivisible loads need route permissions from the authorities having jurisdiction over the area of movement.

The permission names the approved route. The driver carries a copy of the permission letter and the uploaded documents during the move, and the transporter declares the trip closed when it ends.

Trailer types HT-1 to HT-13

MoRTH groups modular hydraulic trailer combinations into thirteen types for National Highway permissions. The weights below are gross vehicle weights without the puller tractor, at 18 tonnes per axle row. MoRTH’s bridge charts take the puller as a three-axle tractor of 25 tonnes with ballast. For HT-10 to HT-13, the weight of the bolster or girder attachment counts in the gross weight. On some bridges the permitted weight for HT-4 to HT-13 is lower.

HT-1
4 axle rows, 72 t
HT-2
6 axle rows, 108 t
HT-3
8 axle rows, 144 t
HT-4
10 axle rows, 180 t
HT-5
12 axle rows, 216 t
HT-6
14 axle rows, 252 t
HT-7
16 axle rows, 288 t
HT-8
18 axle rows, 324 t
HT-9
20 axle rows, 360 t
HT-10
8 + 8 axle rows with turntable bolster, 288 t
HT-11
10 + 10 axle rows with turntable bolster, 360 t
HT-12
14 + 14 axle rows with girder arrangement, 504 t
HT-13
16 + 16 axle rows with girder arrangement, 576 t

How the National Highway permission works

MoRTH’s circular of 27 October 2025 sets the process. The fee is charged for each 50 km, or part of 50 km, of National Highway on the trip, by trailer type; the rates follow the steps.

1. Register

Consignor, consignee and transporter each register once on the portal, with PAN, GSTIN where applicable, address proof and a contact person. The registered email address is the login.

2. Cargo details

The consignor or consignee enters the cargo’s length, width and height, its weight including packing, and the origin and destination, uploads a signed declaration of these details on its letterhead, and nominates the transporter.

3. Vehicles, drivers and route

The transporter adds the puller tractor, each trailer module and the drivers. The portal checks registration, permit, fitness, tax and insurance on VAHAN and driving licences on SARATHI. The route needs at least one station for every 100 km, and each vehicle needs a location tracking device that meets AIS 140.

4. Bridge check

The portal does not accept a route with a bridge unsuitable for the trailer type. For HT-4 to HT-13, regional officers review the route within 7 days of the application; if they do not, the route is treated as feasible.

5. Fee and permission

For HT-1 to HT-3 the permission is generated in real time once the route is accepted and the fee paid online. For HT-4 to HT-13 it is generated once the fee is paid after the bridge check. The fee must be paid within 7 days of the demand, or the approval lapses.

6. Journey

The journey must start within 7 days of the permission, or the transporter enters a revised start date on the portal before then. Within 15 days of reaching the destination, the transporter declares the trip complete.

Fee per 50 km, HT-1 to HT-3
₹1,200
Fee per 50 km, HT-4 to HT-6
₹2,400
Fee per 50 km, HT-7 to HT-9
₹3,600
Fee per 50 km, HT-10 to HT-13
₹4,800

Documents to have ready

The MoRTH portal asks for the following.

  • PAN, GSTIN where applicable and address proof for the consignor, consignee and transporter
  • Cargo length, width and height in metres, and weight including packing in tonnes
  • Origin and destination with PIN codes, and the consignor’s and consignee’s names, addresses, contact details and GSTIN or PAN
  • A declaration of the cargo details on the consignor’s or consignee’s letterhead, signed by a competent person
  • Registration numbers of the puller tractor and every trailer module, with valid permit, fitness, tax and insurance
  • For each driver, a driving licence valid for heavy transport vehicles
  • The transporter’s online self-declarations, including that the trailers are technically fit and spread the load evenly over all axle rows

Route survey and bridge checks

A route survey before the move records the bridges and culverts, overhead cables and structures, turning radii, gradients and road condition along the planned route, and finds diversions where a section cannot take the load.

For a loaded height over 4.75 m, the route must avoid overhead structures, bridges at railway crossings (RoBs and RuBs) and underpasses that limit height; otherwise the permission leaves out those under-bridges, foot over-bridges and overpasses, and the transporter makes diversions around them.

On National Highways, MoRTH does not permit ODC/OWC movement over these bridges:

  • Simply supported bridges with a span over 50 m that are not designed for IRC Special Vehicle (SV) loading
  • Bridges of any other type that are not designed for SV loading
  • Bridges designed by the limit state method and not for SV loading
  • Bridges marked distressed (orange or red) on the portal, rated below capacity or already under a load restriction
  • For HT-12 and HT-13, bridges other than the simply supported type, even when designed for SV loading

Escorts, markings and bridge crossings

MoRTH attaches these conditions to every National Highway permission.

  • A pilot vehicle accompanies the load, showing prominently that an ODC/OWC consignment is passing
  • Danger flags and lights; yellow and black zebra stripes across the full width at front and rear, with retro-reflective stickers; red lamps at the extreme positions for night driving and parking; red flags on both sides by day
  • Trailer modules may be coupled lengthwise for a single consignment, never side by side, with no axle row over 18 tonnes
  • Bridges are crossed under the supervision and escort of the transporter’s responsible staff, with no other vehicle on the bridge
  • On a bridge: 5 km/h or less, no braking, and the load’s centreline within 300 mm of the carriageway’s centreline
  • Transporter staff inspect each bridge before and after the crossing and report any distress to the regional officers by email
  • Bridge crossings are timed for the lowest water current, with special care in the monsoon

Typical timelines and what drives them

The National Highway permission has fixed time limits. HT-1 to HT-3 permissions are generated in real time. For HT-4 to HT-13, the bridge review takes up to 7 days from the application. The fee demand stays open for 7 days, and the journey must start within 7 days of the permission.

The time to plan and complete a move also depends on:

  • The trailer type: HT-4 and above need the regional officers’ bridge review
  • Bridges on the route that are barred for the trailer type, and the diversions around them
  • Overhead clearance, when the loaded height is over 4.75 m
  • Roads outside the National Highway network, which need permission from the authorities responsible for them
  • The route survey, the engineering, and the loading and lashing of the cargo
  • Distance and travel speed, including 5 km/h or less on each bridge

What to send for a quote

A transport plan starts from the cargo and the route. Send:

  • Length, width and height of each piece, and its weight
  • Centre of gravity and lifting or lashing points, if known
  • Drawings or photos of the cargo
  • Whether the cargo can be divided into smaller pieces
  • Pickup and delivery addresses, including the port for an import or export
  • How the cargo will be loaded and unloaded at each end
  • Required dates