1. Register
Consignor, consignee and transporter each register once on the portal, with PAN, GSTIN where applicable, address proof and a contact person. The registered email address is the login.
Guide
In India, a load is over-dimensional (ODC) or over-weight (OWC) when it cannot be carried within the vehicle size limits of rule 93 of the Central Motor Vehicles Rules, 1989, or the axle-weight limits notified by the Ministry of Road Transport and Highways (MoRTH). On National Highways, a single indivisible load on modular hydraulic trailers moves under an online MoRTH permission.
This guide sets out the limits, permits, documents, route and bridge checks, escorts and timelines as of October 2026, with the official sources listed at the end.
Rule 93 of the Central Motor Vehicles Rules, 1989 sets the maximum width, length and height of each vehicle category. Cargo that would take a vehicle past these limits is over-dimensional cargo (ODC).
For an indivisible load, rule 93 allows two relaxations. The load may project 200 mm beyond each side of a vehicle 2.6 m wide, with the projecting part painted or taped in yellow and black reflective marking and a red lamp at the rear and a white lamp at the front of each extreme end. The vehicle may also be up to 4.75 m high.
Rule 93 defines an indivisible load as cargo that cannot be divided without extreme effort, expense or risk of damage, and cannot be carried without exceeding the permissible mass or dimensions of the vehicle and roads.
MoRTH notification S.O. 3467(E) of 16 July 2018, as amended by S.O. 3881(E) of 6 August 2018, sets the maximum safe weight for each axle type under section 58 of the Motor Vehicles Act, 1988, and caps gross vehicle weight. Cargo that would take a vehicle past these weights is over-weight cargo (OWC).
On single axles with four tyres, and on tandem axles and tri-axles of rigid vehicles and trailers, pneumatic suspension allows 1 tonne more per axle. Modular hydraulic trailers may carry indivisible goods of any weight, subject to the regulatory approvals required. S.O. 3467(E) limits each axle row of a modular hydraulic trailer to 18 tonnes, and MoRTH’s National Highway permissions apply the same limit.
On National Highways, MoRTH grants online permission for a single indivisible ODC/OWC consignment on modular hydraulic trailers, types HT-1 to HT-13, through its ODC/OWC portal at morth-owc.nic.in. Regional officers of MoRTH, the National Highways Authority of India (NHAI) and the National Highways and Infrastructure Development Corporation (NHIDCL) review the bridges on the route.
Roads that are not National Highways need permission from the authorities with jurisdiction over them. MoRTH’s 2018 advisory on axle weights says modular hydraulic trailers carrying single indivisible loads need route permissions from the authorities having jurisdiction over the area of movement.
The permission names the approved route. The driver carries a copy of the permission letter and the uploaded documents during the move, and the transporter declares the trip closed when it ends.
MoRTH groups modular hydraulic trailer combinations into thirteen types for National Highway permissions. The weights below are gross vehicle weights without the puller tractor, at 18 tonnes per axle row. MoRTH’s bridge charts take the puller as a three-axle tractor of 25 tonnes with ballast. For HT-10 to HT-13, the weight of the bolster or girder attachment counts in the gross weight. On some bridges the permitted weight for HT-4 to HT-13 is lower.
MoRTH’s circular of 27 October 2025 sets the process. The fee is charged for each 50 km, or part of 50 km, of National Highway on the trip, by trailer type; the rates follow the steps.
Consignor, consignee and transporter each register once on the portal, with PAN, GSTIN where applicable, address proof and a contact person. The registered email address is the login.
The consignor or consignee enters the cargo’s length, width and height, its weight including packing, and the origin and destination, uploads a signed declaration of these details on its letterhead, and nominates the transporter.
The transporter adds the puller tractor, each trailer module and the drivers. The portal checks registration, permit, fitness, tax and insurance on VAHAN and driving licences on SARATHI. The route needs at least one station for every 100 km, and each vehicle needs a location tracking device that meets AIS 140.
The portal does not accept a route with a bridge unsuitable for the trailer type. For HT-4 to HT-13, regional officers review the route within 7 days of the application; if they do not, the route is treated as feasible.
For HT-1 to HT-3 the permission is generated in real time once the route is accepted and the fee paid online. For HT-4 to HT-13 it is generated once the fee is paid after the bridge check. The fee must be paid within 7 days of the demand, or the approval lapses.
The journey must start within 7 days of the permission, or the transporter enters a revised start date on the portal before then. Within 15 days of reaching the destination, the transporter declares the trip complete.
The MoRTH portal asks for the following.
A route survey before the move records the bridges and culverts, overhead cables and structures, turning radii, gradients and road condition along the planned route, and finds diversions where a section cannot take the load.
For a loaded height over 4.75 m, the route must avoid overhead structures, bridges at railway crossings (RoBs and RuBs) and underpasses that limit height; otherwise the permission leaves out those under-bridges, foot over-bridges and overpasses, and the transporter makes diversions around them.
On National Highways, MoRTH does not permit ODC/OWC movement over these bridges:
MoRTH attaches these conditions to every National Highway permission.
The National Highway permission has fixed time limits. HT-1 to HT-3 permissions are generated in real time. For HT-4 to HT-13, the bridge review takes up to 7 days from the application. The fee demand stays open for 7 days, and the journey must start within 7 days of the permission.
The time to plan and complete a move also depends on:
A transport plan starts from the cargo and the route. Send:
As of October 2026. Every legal figure on this page is taken from the official texts below. Rules and fees change, so check the current text before planning a move. This guide is general information, not legal advice.
Mega Move India Private Limited moves ODC on its own fleet: 40 hydraulic axle lines, 4 heavy-duty pullers, 18 lowbed trailers, 10 flatbed trailers and 2 heavy-duty spacers. Offices in Navi Mumbai, Vapi, Hisar and Chennai.